San Juan Neighbourhood Bikeway Improvements
Current Progress
Construction is ongoing and should be expected along the route between October and December 2026. This section will be updated with specific timing when available.
📅 October 15-18: Pavement marking work is scheduled to take place along the route. To minimize traffic impacts, this work will be carried out in the evenings.
Residents may notice temporary noise, lighting and work vehicles while crews are on site. We appreciate your patience as this work is completed.
📅 November 9: Speed hump installation on Simon Road (near Birring Place) and Malton Road (near Eric Road).
Single lane alternating traffic (SLAT) will be in effect during installation. Please expect minor delays.
📅 Late 2026: Flashing beacon installation work to take place at Tyndall Avenue and San Juan. Please adhere to any temporary signage.
About the project
The District will be installing new signage, pavement markings, and traffic calming measures in the Gordon Head neighbourhood. The project area is an east-west route that includes:
- San Juan Avenue: between Gordon Head Road and Shelbourne Street
- Elnido Road: between Shelbourne Street and Harvest Lane Park
- Jamaica Road: between Harvest Lane Park and Parkside Crescent
- Winchester Road: between Parkside Crescent and Glendenning Road
- Glendenning Road: between PKOLS and Mount Douglas Cross Road
- Malton Avenue: through to Simon Road
- Simon Road: to Mckenzie Avenue
What work is being done?
The planned improvements will include:
- New bike route signage along the full route
- New “sharrow” pavement markings along the full route
- Updated speed limit signage
- Minor brush trimming to improve sightlines and visibility
Traffic calming measures on:
- Simon Road: two speed humps between Mckenzie Ave and Eric Rd
- Parkside Cres and Winchester Rd Intersection: traffic circle
- San Juan Ave: Crosswalk pinch points on midblock crossings near Majestic Drive
Bike crossing improvements at:
- San Juan and Tyndall
- San Juan and Shelbourne
Why are we doing this?
These improvements will grow Saanich’s long-term cycling network and provide a comfortable east-west connection beginning near Arbutus Cove through to Braefoot Park and the Mckenzie corridor.
Updated signage and “sharrows” will encourage slower speeds, improve wayfinding, and help users connect to nearby destinations and travel corridors.
This route was identified as part of the wider Neighbourhood Bikeways Identification and Prioritization Project. It involved technical analysis and community input to determine bikeway routes designed to promote safer travel throughout Saanich.
Project Location

Project Timeline
Estimated start: October 2026
Estimated completion: December 2026*
* If there are weather delays, some paint marking work may take place in spring 2027.
What to expect
Some temporary changes to pedestrian and vehicle access may be needed during construction. This may include possible delays while work is taking place. Efforts will be made to minimize inconvenience for residents and maintain access to homes, schools, and transit.
During construction, please note any Traffic Control Personnel during construction and follow their directions and any construction zone signage.
Stay Informed
Follow this project page for updates on construction progress, traffic impacts, and project development.